Timeline
Sleeping Giant School
Design: November 2019 – Summer 2020
Construction: Summer 2020 – Fall/Winter 2021
Strawberry Park Elementary School
Design: November 2019 – Spring 2020
Construction: Summer 2020 – Fall 2020
Soda Creek Elementary School
Design: November 2019 – Spring 2020
Construction: Summer 2020 – Early 2021
Steamboat Springs Middle School
Design: November 2019 – Spring 2020
Construction: Summer 2020 – Late 2020
Steamboat Springs High School
Design: December 2019 – Fall 2020
Construction: Spring 2021 – Summer 2022
North Routt Community Charter School
Design: Spring 2020 – Fall 2020
Construction: Spring 2021 – Fall 2021
Yampa Valley High School /B&G Club
Design: Spring 2020 – Fall 2020
Abatement: Summer/Fall 2020
Construction: Fall 2020-Spring 2021
7th St. Restroom Improvements
Design: December 2019 – Spring 2020
Construction: Summer 2020
News
District begins process to create boundaries for new school, provides COVID-19 update. Read more
New Steamboat Springs School District PK–8 School Gets a Name: Sleeping Giant School. Read more
Read this statement on the placement of power lines on the PK-8 property here
Learn about the PK-8 school naming process here
Review the Steamboat II traffic study